>Master Bathroom Remodel
September 11 - December 20, 2002
Update: January 27-28, 2004
![]() |
This is what the bathroom looked like when we purchased the
house.
Called the bruised bathroom, for its black, blue and purple color scheme. |
September 11, 2002 - End of Day 1.
Everything has been removed. You are looking at what used to be the vanity. |
|
September 11, 2002 - End of Day 1.
Looking through the door at the shower. Notice the pile of debris. above that used to be the wall heater.
|
|
September 11, 2002 - End of Day 1.
Inside the shower. |
|
September 11, 2002 - End of Day 1.
Inside the shower looking through the wall. This is the old shower valve. |
|
September 11, 2002 - End of Day 1.
Inside the bathroom looking towards the door. |
|
September 11, 2002 - End of Day 1.
Looking at the upper part of the shower door. Notice the abandoned electrical box. From the outside of the house, this was the very old meter box. |
|
September 11, 2002 - End of Day 1.
This is the vanity. It is standing on end and you are looking at the bottom. At the top, notice the particle board has expanded due to water damage.
|
|
September 11, 2002 - End of Day 1.
A close up of the water damaged vanity. |
|
September 12, 2002 -Day 2. Lunch time.
The plumber has started. Notice how the drywall is opened up on the back wall and you can see the sun light from the water heater room. |
|
September 12, 2002 - Day 2. Lunch time.
The water heater is removed to gain access to the hot and cold water lines. Notice the hard working plumber in the lower left corner. This room will be the termination point for water for this bathroom. This will make it MUCH easier when we get ready to repipe the entire house. |
|
September 12, 2002 - Day 2.
The new copper pipe to the water heater. |
|
September 13, 2002 - Day 3.
What a night. You can see in this picture the old galvanized water pipes have been capped off, but the old pipes to the shower broke just below the concrete. Without the tools to fix it, the water remained shut off overnight, meaning a stay a the local motel. |
|
September 13, 2002 - Day 3. Morning.
The new shower valve is installed. |
|
September 16, 2002 - Day 4. Morning.
Here is the replacement pipe that broke causing us to be without water Thursday night. |
|
September 16, 2002 - Day 4. Morning.
This is a ground level shot showing the shower frame NOT touching the ground. Behind the wood you can see the temporary capped cold water line and the previously capped hot water line (covered with duct tape). |
|
September 17, 2002 - Day 5. Morning.
Yesterday they cut more of the floor and dug down until they hit dirt. |
|
September 17, 2002 - Day 5. Morning.
Looking down the hole you can see the pipe they were looking for and found another pipe crossing its path. We think this pipe goes outside, but we are not sure. |
|
September 17, 2002 - Day 5. Lunch Time.
They have started rebuilding the shower frame with new wood. Notice the new shower door way. |
|
September 17, 2002 - Day 5. Lunch Time.
They patch part of the floor so they could build the shower frame. They still have to finish removing the old galvanized pipe(s) from under the concrete. |
|
September 17, 2002 - Day 5. Lunch Time.
Reminder to self. There is a vent pipe in the shower wall. |
|
September 17, 2002 - Day 5. Lunch Time.
New wood used on upper shower door. Taken without flash. |
|
September 17, 2002 - Day 5. Lunch Time.
Same shot as before, but now with flash. |
|
September 18, 2002 - Day 6. Morning.
Yesterday the hot mop crew came in and applied tar to build the shower pan. |
|
September 18, 2002 - Day 6. Morning.
I don't know why I was surprised that the whole house smelled like tar all night. |
|
September 18, 2002 - Day 6. Morning. | |
September 18, 2002 - Day 6. Lunch time.
The crew rented a jackhammer and broke up more concrete. |
|
September 18, 2002 - Day 6. Lunch time.
This exposed more pipes underground. Notice the rusting, galvanized pipes UNDER the house. I don't think it would be very good if one of these pipes were to break. |
|
September 18, 2002 - Day 6. Lunch time.
I authorized them to finish opening up the floor and remove as much of the galvanized pipes as possible. |
|
September 19, 2002 - Day 7. Morning.
You can see the tar paper is now installed in the shower. But more importantly, there is a bigger hole in the bathroom. The major discovery is that a 1" main water line come from the front of the house and first tees off to the toilet, then the sink, then to the shower and hot water heater. We were hoping the water line would start with the water heater and then go to the bathroom.
|
|
September 19, 2002 - Day 7. Morning.
A better shot of the tar paper and water is now in the shower pan to test for leaks.
|
|
September 19, 2002 - Day 7. Morning.
The plan for today is to not touch the main 1" line, but to go from this Tee into a 3/4" line and up to the water heater. On the way up to the water heater, we will tee again and feed the bathroom. |
|
September 19, 2002 - Day 7. Morning.
This the first tee going to the toilet. To the left is the sink (not displayed). |
|
September 19, 2002 - Day 7. Morning.
These galvanized pipes will be replaced with copper in the water heater room. |
|
September 19, 2002 - Day 7. Morning.
Here is the main water line feeding the water heater. This will get replaced today. |
|
September 19, 2002 - Day 7. Morning.
This is the old cold water line going to the shower. Note it is now capped off. |
|
September 20, 2002 - Day 8. Morning.
The new copper is now installed. You can see an old tee underground is capped off. |
|
September 20, 2002 - Day 8. Morning.
This is where the toilet is going. The original cold water line is now capped off below the concrete. The new copper is above it. |
|
September 20, 2002 - Day 8. Morning. | |
September 20, 2002 - Day 8. Morning.
New hot and cold copper pipe to the shower. |
|
September 20, 2002 - Day 8. Morning.
New copper pipe for the water heater. |
|
September 20, 2002 - Day 8. Morning.
Notice the cold water tee that now feeds the bathroom. |
|
September 20, 2002 - Day 8. Morning.
This the cold water line coming up to feed the water heater. |
|
September 20, 2002 - Day 8. Morning.
This is the tap from the old galvanized to copper to feed the water heater and bathroom. The right side goes outside to the faucet. The left side is the feed from the front of the house. |
|
September 23, 2002 - Day 9. Morning.
On Friday, they filled in the holes and poured concrete. |
|
September 23, 2002 - Day 9. Morning. | |
September 23, 2002 - Day 9. Morning.
Here is the concrete in the shower. This raised the floor level to the drain. |
|
September 23, 2002 - Day 9. Morning.
This looking though the bathroom wall into the water heater room. |
|
September 23, 2002 - Day 9. Morning.
This is the water heater room. |
|
September 24, 2002 - Day 10. Morning.
Yesterday they started the drywall and cement board (in the shower). |
|
September 24, 2002 - Day 10. Morning.
As you can see there is still more to do. |
|
September 25, 2002 - Day 11. Morning.
Not much was done yesterday. The only change that I saw was the soldering of the shower head receptacle. |
|
September 25, 2002 - Day 11. Morning.
They still need to move the light's electrical box over to make room for the new lights. The new location is marked with penciled square. |
|
September 25, 2002 - Day 11. Morning.
The wall next to the other electrical box still needs some clean-up. |
|
September 25, 2002 - Day 11. Lunch Time.
As of lunch, the drywall appeared to be done inside the bathroom. He was working in the water heater room. Here you can see the electrical box on the left has been moved to its new location and the patching fixed near the electrical box on the right. |
|
September 25, 2002 - Day 11. Lunch Time.
The old wall heater hold is now covered up. |
|
September 25, 2002 - Day 11. Lunch Time.
The light switch area is also cleaned up. |
|
September 26, 2002 - Day 12. Morning.
It looks like all drywall work is completed and the primer paint was applied to the bathroom. |
|
September 26, 2002 - Day 12. Morning.
The drywall work was completed inside the water heater room. |
|
September 27, 2002 - Day 13. Morning.
The floor has been started! All the whole tiles were installed. |
|
September 27, 2002 - Day 13. Morning.
Today the cut tiles should go in. |
|
September 30, 2002 - Day 14. Morning.
Last Friday, the finished the floor. You can see all the cut tiles are in and the grout installed. |
|
September 30, 2002 - Day 14. Morning.
More pictures of our nice new floor. |
|
September 30, 2002 - Day 14. Morning.
Hopefully the shower tile will begin soon. |
|
October 1, 2002 - Day 15. Morning.
The vanity has arrived and was painted! |
|
October 1, 2002 - Day 15. Morning.
The water heater has been installed and the inside has been painted. We also added a water heater pan to prevent future floods. |
|
October 2, 2002 - Day 16. Morning
The Cabinet and countertop are now sitting in place, but not secured. |
|
October 2, 2002 - Day 16. Morning
The shower tile has begun. |
|
October 3, 2002 - Day 17. Morning.
The bathroom really began to take shape! The toilet was installed and works! I had to go out and buy a seat. The mirror was installed, the faucet was install and hooked up, except for the drain. |
|
October 3, 2002 - Day 17. Morning.
The wall lights were installed--upside down. |
|
October 3, 2002 - Day 17. Morning.
We expect the drain line to be connected to the sink today. The water lines are already connected. |
|
October 4, 2002 - Day 18. Morning.
The lights are not pointing in the right direction. |
|
October 4, 2002 - Day 18. Morning.
About half of the tile is installed in the shower. |
|
October 4, 2002 - Day 18. Morning.
Here are the new soap dish holder and corner shelf-something we did not have before. I hope this doesn't make it too cluttered. |
|
October 4, 2002 - Day 18. Morning.
They installed the towel holders upside down. I didn't think it was possible, but it is. |
|
October 4, 2002 - Day 18. Morning.
Installed the TP holder. |
|
Saturday, October 5, 2002 - Day 19. Evening.
Its Saturday and they finished the shower tile, except for the floor. |
|
Saturday, October 5, 2002 - Day 19. Evening.
Some grouting has begun. |
|
Saturday, October 5, 2002 - Day 19. Evening.
There is still much to do, like fixing up this corner. |
|
Saturday, October 5, 2002 - Day 19. Evening.
The entry into the shower will have to be redone, it does not angle into the shower. Again the floor has not been started. |
|
Tuesday, October 8, 2002 - Day 21. Morning.
Yesterday's big accomplishment was the finishing of the tile and grout. |
|
Tuesday, October 8, 2002 - Day 21. Morning.
There is still some grout cleanup to do. |
|
Tuesday, October 8, 2002 - Day 21. Morning.
Its looking a lot like a real bathroom now, a very dusty bathroom. |
|
Tuesday, October 8, 2002 - Day 21. Evening.
By the end of Tuesday, October 8, the shower fixtures were installed, however we discovered that the piece between the wall and the handles was missing. Actually Price Pfister doesn't make this sleeve in bushed nickel, but they are sending me a polished chrome piece for free. |
|
Tuesday, October 8, 2002 - Day 21. Evening.
Work was also completed on the sink. It now fully works-with minimal leaks. They are taking a couple of days off to let some plaster dry. They are suppose to show up on Saturday, Oct 12 to continue. This will give us a few days of rest! |
|
Tuesday, October 15, 2002 - Day 22. Evening.
More progress was made. The door was painted and installed. |
|
Tuesday, October 15, 2002 - Day 22. Evening.
Long sleeves and covers arrived from Price Pfister to cover the distance between the handles and the wall. |
|
Tuesday, October 15, 2002 - Day 22. Evening.
The area around the skylight in the shower was painted. |
|
Tuesday, October 15, 2002 - Day 22. Evening.
All the handles are now installed. |
|
Friday, October 18, 2002 - Day 23. Evening.
The shower handle trim is now fixed. |
|
Friday, October 18, 2002 - Day 23. Evening.
This is the cracked mirror that should be replace soon. |
|
Friday, October 18, 2002 - Day 23. Evening.
Its hard to see, but additional grout is needed. This is the floor and wall of the shower. |
|
Friday, October 18, 2002 - Day 23. Evening.
More grout or patching for the shower head is also needed. The third load of trash was removed, but there is still more to remove. Its amazing how much trash one little bathroom can make. |
|
Thursday, October 24, 2002 - Day 24. Evening
The new (replacement) mirror arrived and was installed. |
|
Thursday, October 24, 2002 - Day 24. Evening
Tri-Tech says they fixed the leaking drain, but I still saw it leak. |
|
Thursday, October 24, 2002 - Day 24. Evening
The countertop was secured and caulked. |
|
Thursday, October 24, 2002 - Day 24. Evening
The drain cover was installed, but the grouting was not fixed or sealed. |
|
Bathroom Remodel Part II - The Redo |
Day 25. Friday, November 8, 2002 Lunch Time. Today it was decided to redo the shower and fix all the outstanding issues. |
Day 26. Thursday, November 14, 2002 Lunch Time
Now we start over. By lunch time all tile was removed and the inside of the shower walls were removed down to the hot mop area. |
|
Day 26. Thursday, November 14, 2002 Lunch Time.
Much better the second time. This crew was very careful with the sink counter top, floor and rest of the house. |
|
Day 26. Thursday, November 14, 2002 Lunch Time.
The drywall was fixed and sanded. This smoothed out the various rips and bumps. When they left for the day, they removed all the trash and swept up with their own broom! This made Jennifer very happy! |
|
Day 27. Friday, November 15, 2002 Evening.
Or day 2 of the redo and already the cement board is installed. |
|
Day 27. Friday, November 15, 2002 Evening.
Cement was added at the bottom to help straighten out the walls. |
|
Day 28. Monday, November 18, 2002 Evening.
Tiling has begun! |
|
Day 28. Monday, November 18, 2002 Evening.
The checkerboard pattern was placed in, but now some tiles will have to be removed to install the soap dish and corner shelf. |
|
Day 28. Monday, November 18, 2002 Evening.
About half of the walls were completed. |
|
Day 29. Tuesday, November 19, 2002 Evening.
The walls are basically complete with tile. |
|
Day 29. Tuesday, November 19, 2002 Evening.
The tiles go all the way to the ceiling/skylight. |
|
Day 29. Tuesday, November 19, 2002 Evening.
Most of the door way is done. |
|
Day 29. Tuesday, November 19, 2002 Evening.
But the top, bottom and around the door still need to be done. |
|
Day 30. Wednesday, November 20, 2002 Evening.
The floor was mostly completed today. |
|
Day 31. Thursday, November 21, 2002 Evening.
Lots of work was done today. Here one of the defective floor tiles was removed and replaced. |
|
Day 31. Thursday, November 21, 2002 Evening.
Here another floor tile was removed and replaced. |
|
Day 31. Thursday, November 21, 2002 Evening.
It looks like the shower tiles are now complete, except grouting. Here you can see the tiles around the door are done. |
|
Day 31. Thursday, November 21, 2002 Evening.
Here are the tiles around the top and the pattern now matches. |
|
Day 31. Thursday, November 21, 2002 Evening.
Looks like the floor is complete. |
|
Day 31. Thursday, November 21, 2002 Evening.
And all the base board tiles were installed! |
|
Day 32. Friday, November 22, 2002 Evening.
Grouting was completed. |
|
Day 32. Friday, November 22, 2002 Evening.
The replaced floor tiles were grouted. |
|
Day 32. Friday, November 22, 2002 Evening.
The shower grout looks complete. |
|
Day 32. Friday, November 22, 2002 Evening.
More grouting completed. |
|
Day 32. Friday, November 22, 2002 Evening.
Looking good! |
|
Day 33. Monday, November 25, 2002 Evening.
Today was painting day. Here one of the bedroom walls was painted. |
|
Day 33. Monday, November 25, 2002 Evening.
The inside of the bathroom was repainted. |
|
Day 33. Monday, November 25, 2002 Evening.
The walls outside of the bathroom were also repainted. |
|
Day 34. Wednesday, November 27, 2002 Evening.
Today should be the final day of Tri-Tech's construction. |
|
Day 34. Wednesday, November 27, 2002 Evening.
All the trim was put back on. |
|
Day 34. Wednesday, November 27, 2002 Evening.
They even cleaned the window! |
|
Day 34. Wednesday, November 27, 2002 Evening.
All fixtures were re-installed.
Next step--order shower door, then we should be complete! |
|
Day 35. Friday, December 20, 2002.
The shower door finally arrived and was installed. |
|
Day 35. Friday, December 20, 2002.
After 35 construction days, this project is finally completed!
Or so we thought... |
|
Part III - The leak fix |
|
Day 36. Tuesday, January 27, 2004.
Just over a year past since we thought we were done, but one little problem remained--the shower leaked! After three months of construction, we were not anxious to do any more work on the bathroom, besides, John was coming and with a new baby and a toddler we weren't ready for more construction projects. |
|
Day 36. Tuesday, January 27, 2004.
But in the right corner of the door, water would run out every time we took a shower. The problem, the tile was leaning out of the shower, not into the shower. So, time for Tri-Tech to remove the door and tiles and slope them in. |
|
Day 36. Tuesday, January 27, 2004.
They came out to "look", tried to convince us it was the seal on the door, but quickly discovered we were right about the slope of the tiles, so off went the old tiles. |
|
Day 36. Tuesday, January 27, 2004.
And in with the new--now sloping into the shower. |
|
Day 36. Tuesday, January 27, 2004.
By the end of the first day, the tiles were set. |
|
Day 37. Wednesday, January 28, 2004.
On the second day, the grout was installed and the shower door re-installed.
|
|
Day 37. Wednesday, January 28, 2004.
The End ??? |